End of 2010, CERN launched a R2E program which includes the study of Radiation tolerant power converters design, called R2E Power Converters.

topR2E/EPC Projects

A specific spare strategy covers a possible rotation of unit of complete areas in case some crash program is required.

Project Total Project Qty
Total LHC Op. LHC Spares LHC R2E-Test
R2E-FGClite
Budget Code: 99 690
1400 1090 218 30+20
R2E-Rad-DIM
Budget Code: 99 691
3767 1528+1500 252+90 30
R2E-LHC120A-10V
Budget Code: 99 692
102
R2E-LHC600A-10V
Budget Code: 99 693
162 120 32 10
R2E-LHC4-6-8kA-08V
Budget Code: 99 694
95 64 ≈15 ≈2
R2E-Study
Budget Code: 99 695
NA

Details of Quantities to be produced in the whole R2E process Figures    -    Details

topR2E/EPC Planning

Project Planning
2011 2012 2013 2014 2015 2016 2017 2018 2019
R2E-FGClite
Budget Code: 99 690
  Design Design
Type Test
Design
Cpts Purchase
Pre-Series
Batch-Test
Unit Test
Prod.
Install.
Production
Install.
 
R2E-Rad-DIM
Budget Code: 99 691
    Design
Type Test
Design
Cpts Purchase
Pre-Series
Batch-Test
Unit Test
Prod.
Install.
Production
Install.
 
R2E-LHC120A-10V
Budget Code: 99 692
Eval.  
R2E-LHC600A-10V
Budget Code: 99 693
    Design
Prototype
Pre-Series
Rad-Test
Components
Purchase &
Rad-Qual.
Production Production Reception
Install.
R2E-LHC4-6-8kA-08V
Budget Code: 99 694
  Design Design
Prototype
Pre-Series
Rad-Test
Components
Purchase &
Rad-Qual.
Production Production Reception
Install.
R2E-Study
Budget Code: 99 695
Theoric
Test
Theoric
Test
Tester
Design
Component Qualif.
 

Projective Planning of the full R2E-EPC Program (budget spending profile .xls)
Current    -    History

topR2E/EPC Irradiated Units Management

Irradiated units management strategy is organized and defined at the level of the group SY-EPC.

topR2E/EPC Project Management

R2E projects have been organized for a maximum efficiency in dissociating the already hard power design phase from the rad-tolerant consideration. This allows people and teams working in parallel, limiting the impact of each team on each other. A fundamental principle highlighted in this organisation is the natural flexibility of a power converter designer regarding to the component choice, once all choice criteria have been identified in the considered design.
Of course some additional design rules are taken in account at the design level, but not changing drastically the original design methods however aiming for a simple design relying on robust components of few families and types.

R2E Strategy: EPC Team Organization

R2E Strategy: EPC - Power Converter Team Organization .vsd

R2E Strategy: EPC Team Organization

R2E Strategy: EPC - Power Converter Manpower Affectation .vsd