Project Follow-up



topProvide Booster MPS



topProvide Booster MPS Trims

LIU-PSB 5.2
WU 174178
PLAN 10311
completed
Workunit holder: Fulvio Boattini
Budget Code: 99238
Due date: December 2018
Circuits BR.RQFO, BR.RQDE, BR.RQ.SP
BR14.RTBH15L1, BR14.RTBH16L2, BR14.RTBH.SP
BR23.RTBH15L1, BR23.RTBH16L2, BR23.RTBH.SP
Deliverables 2+1 Isolated APOLO_2S Converters for BR.QF & BR.QD
4+2 COMET Converters for the Injection/Ejection trims.
Documentation
  • Magnet
Installation data


topProvide control electronics

LIU-PSB 5.2
WU 126435
completed
Workunit holder: Benjamin Todd
Budget Code: 99233
Due date: December 2017
Deliverables FGC3 electronics, chassis and PSU
Documentation
  • Functional specification
Installation data
  • ? racks
  • Width: 600mm, Depth: 900mm, Height: xmm, Weight: xkg
  • Maximal distance to converters: 100m
  • Installation Procedure


topPerform ALG1&2 upgrade

LIU-PSB 5.2
WU 91572
PLAN 10313
completed
Workunit holder: Jean-Marc Cravero
Budget Code: 99239
Due date: September 2019
Circuits BE.RSMH15L1, BT1.RSMV10, BT4.RSMV10, BT2.RSMV20
Deliverables 4+1 MegaDiscaP
Documentation
Installation data
  • bdg. 361-2-007(BHP)
  • 5 racks
  • Width: 1150mm, Depth: 1000mm, Height: xmm, Weight: xkg


topProvide MidiDiscap

LIU-PSB 5.2
WU 91573
PLAN 10314
completed
Workunit holder: Jean-Marc Cravero
Budget Code: 99239
Due date: August 2019
Circuits BE1.RDHZ11L1, BE1.RDHZ4L1, BE1.RDVT11L1, BE1.RDVT4L1, BE2.RDHZ11L1, BE2.RDHZ4L1, BE2.RDVT11L1, BE2.RDVT4L1, BE3.RDHZ11L1, BE3.RDHZ4L1, BE3.RDVT11L1, BE3.RDVT4L1, BE4.RDHZ11L1, BE4.RDHZ4L1, BE4.RDVT11L1, BE4.RDVT4L1,
BT.RDVT50, BT.RDVT60,
BT2.RDVT10, BT3.RDVT10,
BT1.RDHZ10, BT2.RDHZ10, BT2.RDVT40, BT3.RDHZ10, BT3.RDVT30, BT4.RDHZ10,
BTM.RDHZ10, BTM.RDVT10,
BTP.RDHZ10, BTP.RDHZ20, BTP.RDHZ30, BTP.RDHZ40, BTP.RDVT10, BTP.RDVT20, BTP.RDVT30, BTP.RDVT40, BTP.RDVT50
Deliverables 37+4 MidiDiscap Converters
Documentation
Installation data
  • bdg 361-1-012(BCER)
  • Width: 600mm, Depth: 900mm, Height: 42U, Weight: 240kg
  • Maximal distance to load: 100m


topProvide Transfer bendings

LIU-PSB 5.2
WU 91574
PLAN 10316, 11388
completed
Workunit holder: Ivan Josifovic
Budget Code: 99240
Due date: August 2019
Circuits BT.RQNO10, BT.RQNO20, BT.RQNO30, BT.RQNO40, BT.RQNO50
(BTP.RQNO10)
BTP.RQNO20, BTP.RQNO30, BTP.RQ35, BTP.RQNO50, BTP.RQNO55, BTP.RQNO60
BT1.RBVT10, BT4.RBVT10, BT2.RBVT20
BT2.RDVT20, BT3.RDVT20, BT3.RDVT40,
BTM.RQNO05, BTM.RQNO10, BTM.RQNO20,
BR1.RBDL, BR2.RBDL, BR3.RBDL, BR4.RBDL.
Deliverables 24+3 SIRIUS Converters
Documentation
Installation data
  • bdg. 361-2-007(BHP)
  • Width: 1200mm, Depth: 900mm, Height: 2000mm, Weight: 700kg
  • Maximal distance to load: 100m


Circuits BTY.RBVT101, BTY.RBVT116
BR.RONOH0, BR.RXNOH0.
Deliverables 4+2 SIRIUS_2p Converter
Documentation
  • EIS: Isolde
Installation data
  • bdg. 361-2-007(BHP)
  • Width: 1800mm, Depth: 900mm, Height: 2000mm, Weight: 1100kg
  • Maximal distance to load: 100m


Circuits BT.RBHZ10
Deliverables 2+1 SIRIUS_2p converters
Documentation
  • EIS: Two Unipolar version (Isolde + PS) with output thyristor
Installation data
  • bdg. 361-2-007(BHP)
  • Width: 1800mm, Depth: 900mm, Height: 2000mm, Weight: 1100kg
  • Maximal distance to load: 100m


Circuits BTM.RBHZ10
Deliverables 1+1 SIRIUS_4p Converters with 150mF additional capacitor bank
Documentation
Installation data
  • bdg. 361-2-007(BHP)
  • Width: 3200mm, Depth: 900mm, Height: 2000mm, Weight: 2200kg
  • Maximal distance to load: 100m


topBHP Power Converters Installation

LIU-PSB 5.2
WU 202217
PLAN 10305,
10313, 10316,
11388
completed
Workunit holder: Christophe Coupat
Budget Code: 68815
Due date: April 2020
Deliverables Installation for WUs:
126815 BI.BVT Powering
91572 ALG1&2 upgrade
91574 Transfer bendings
Installation data 361-2-007 (BHP)


topUpgrade Canada converters

LIU-PSB 5.2
WU 158196
PLAN 10318
completed
Workunit holder: Serge Pittet
Budget Code: 99240
Due date: August 2019
Circuits None
Deliverables None
Documentation
  • There are only a few CANADA converters candidates for an upgrade.
    The developpement cost and ressources needed for the upgrade is in the same order of magnitude than the full replacement of existing converters. Considering that the existing converters are almost already 20 years old, all circuits has been moved to WU Provide Transfer bendings


topUnused converters

  • BTP.RQNO40: to be removed
  • LBE.KVT10, LBE.KHZ10: to be removed (ECR)