Test Zone dedicated to COMBO-Converters family.
Technical information regarding services requirements.
More info below:
AC-Departures
AC-Departures
Water-Departures
Water-Departures
Ventilation Needs
Ventilation Needs
Network
Network
AC-Departures:
- 1x [63A-3Ph]:
→ 1x for test
- 1x [32A-3Ph]:
→ 1x for test
- 1x [16A-3Ph]:
→ 1x for test
- 2x [16A-1Ph Boxes (4-plugs)]:
→ 1x office (computers)
→ 1x metrology for test
Ventilation Needs:
- <20 kW only for test duration.
Networks:
- 5x RJ45 Ethernet (Gigabit) Plugs
→ 1x RJ45 per AC Departure Network Panel (3x in total)
→ 2x RJ45 for Computers
- 3x FGC3 Plugs
→ 1x FGC3 per AC Departure Network Panel (3x in total)